Improvement Algorithm for Limited Space Scheduling

Selecting construction methods, scheduling activities, and planning the use of site space are key to constructing a project efficiently. Site layout and activity scheduling have been tackled as independent problems. Their interdependence is often ignored at the planning stage and may be dealt with—i...

Full description

Saved in:
Bibliographic Details
Main Author: Zouein, Pierrette (author)
Other Authors: Tommelein, I. (author)
Format: article
Published: 2001
Online Access:http://hdl.handle.net/10725/3120
http://dx.doi.org/10.1061/(ASCE)0733-9364(2001)127:2(116)
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1864513460142866432
author Zouein, Pierrette
author2 Tommelein, I.
author2_role author
author_facet Zouein, Pierrette
Tommelein, I.
author_role author
dc.creator.none.fl_str_mv Zouein, Pierrette
Tommelein, I.
dc.date.none.fl_str_mv 2001
2016-02-18T09:55:03Z
2016-02-18T09:55:03Z
2016-02-18
dc.identifier.none.fl_str_mv 0733-9364
http://hdl.handle.net/10725/3120
http://dx.doi.org/10.1061/(ASCE)0733-9364(2001)127:2(116)
Zouein, P. P., & Tommelein, I. D. (2001). Improvement algorithm for limited space scheduling. Journal of Construction Engineering and Management, 127(2), 116-124.
dc.language.none.fl_str_mv en
dc.relation.none.fl_str_mv Journal of Construction Engineering and Management
dc.rights.*.fl_str_mv info:eu-repo/semantics/openAccess
dc.title.none.fl_str_mv Improvement Algorithm for Limited Space Scheduling
dc.type.none.fl_str_mv Article
info:eu-repo/semantics/publishedVersion
info:eu-repo/semantics/article
description Selecting construction methods, scheduling activities, and planning the use of site space are key to constructing a project efficiently. Site layout and activity scheduling have been tackled as independent problems. Their interdependence is often ignored at the planning stage and may be dealt with—if at all—when construction is underway. Problems that may have had easy solutions if dealt with earlier, may then be expensive to remedy. This paper addresses the combined problem termed “space scheduling” and presents an algorithmic time-space trade-off model for adjusting activity durations and start dates to decrease the need for space over congested time periods. The model characterizes resource space requirements over time and establishes a time-space relationship for each activity in the schedule, based on alternative resource levels. An example illustrates the presented algorithm that generates a feasible space schedule.
eu_rights_str_mv openAccess
format article
id LAURepo_8afe6819fd4ac6f55ca9810dcd84a53e
identifier_str_mv 0733-9364
Zouein, P. P., & Tommelein, I. D. (2001). Improvement algorithm for limited space scheduling. Journal of Construction Engineering and Management, 127(2), 116-124.
language_invalid_str_mv en
network_acronym_str LAURepo
network_name_str Lebanese American University repository
oai_identifier_str oai:laur.lau.edu.lb:10725/3120
publishDate 2001
repository.mail.fl_str_mv
repository.name.fl_str_mv
repository_id_str
spelling Improvement Algorithm for Limited Space SchedulingZouein, PierretteTommelein, I.Selecting construction methods, scheduling activities, and planning the use of site space are key to constructing a project efficiently. Site layout and activity scheduling have been tackled as independent problems. Their interdependence is often ignored at the planning stage and may be dealt with—if at all—when construction is underway. Problems that may have had easy solutions if dealt with earlier, may then be expensive to remedy. This paper addresses the combined problem termed “space scheduling” and presents an algorithmic time-space trade-off model for adjusting activity durations and start dates to decrease the need for space over congested time periods. The model characterizes resource space requirements over time and establishes a time-space relationship for each activity in the schedule, based on alternative resource levels. An example illustrates the presented algorithm that generates a feasible space schedule.PublishedN/A2016-02-18T09:55:03Z2016-02-18T09:55:03Z20012016-02-18Articleinfo:eu-repo/semantics/publishedVersioninfo:eu-repo/semantics/article0733-9364http://hdl.handle.net/10725/3120http://dx.doi.org/10.1061/(ASCE)0733-9364(2001)127:2(116)Zouein, P. P., & Tommelein, I. D. (2001). Improvement algorithm for limited space scheduling. Journal of Construction Engineering and Management, 127(2), 116-124.enJournal of Construction Engineering and Managementinfo:eu-repo/semantics/openAccessoai:laur.lau.edu.lb:10725/31202019-02-01T11:49:49Z
spellingShingle Improvement Algorithm for Limited Space Scheduling
Zouein, Pierrette
status_str publishedVersion
title Improvement Algorithm for Limited Space Scheduling
title_full Improvement Algorithm for Limited Space Scheduling
title_fullStr Improvement Algorithm for Limited Space Scheduling
title_full_unstemmed Improvement Algorithm for Limited Space Scheduling
title_short Improvement Algorithm for Limited Space Scheduling
title_sort Improvement Algorithm for Limited Space Scheduling
url http://hdl.handle.net/10725/3120
http://dx.doi.org/10.1061/(ASCE)0733-9364(2001)127:2(116)