On-site workshop investment problem: A novel mathematical approach and solution procedure

<p>In real-world construction sites, On-Site Workshops (OSW) are installed to accelerate construction activities and facilitate the material handling process. These temporary OSWs are cost-effective, leading to decreasing the material handling cost and project makespan, which indicates their i...

وصف كامل

محفوظ في:
التفاصيل البيبلوغرافية
المؤلف الرئيسي: Nima Moradi (19418821) (author)
مؤلفون آخرون: Vahid Kayvanfar (17876921) (author), Roberto Baldacci (14779375) (author)
منشور في: 2023
الموضوعات:
الوسوم: إضافة وسم
لا توجد وسوم, كن أول من يضع وسما على هذه التسجيلة!
_version_ 1864513508128849920
author Nima Moradi (19418821)
author2 Vahid Kayvanfar (17876921)
Roberto Baldacci (14779375)
author2_role author
author
author_facet Nima Moradi (19418821)
Vahid Kayvanfar (17876921)
Roberto Baldacci (14779375)
author_role author
dc.creator.none.fl_str_mv Nima Moradi (19418821)
Vahid Kayvanfar (17876921)
Roberto Baldacci (14779375)
dc.date.none.fl_str_mv 2023-11-30T15:00:00Z
dc.identifier.none.fl_str_mv 10.1016/j.heliyon.2023.e22678
dc.relation.none.fl_str_mv https://figshare.com/articles/journal_contribution/On-site_workshop_investment_problem_A_novel_mathematical_approach_and_solution_procedure/26642956
dc.rights.none.fl_str_mv CC BY 4.0
info:eu-repo/semantics/openAccess
dc.subject.none.fl_str_mv Information and computing sciences
Data management and data science
Software engineering
Mathematical sciences
Numerical and computational mathematics
On-site workshop
Project scheduling
Multi-mode resource investment problem
Genetic algorithm
dc.title.none.fl_str_mv On-site workshop investment problem: A novel mathematical approach and solution procedure
dc.type.none.fl_str_mv Text
Journal contribution
info:eu-repo/semantics/publishedVersion
text
contribution to journal
description <p>In real-world construction sites, On-Site Workshops (OSW) are installed to accelerate construction activities and facilitate the material handling process. These temporary OSWs are cost-effective, leading to decreasing the material handling cost and project makespan, which indicates their important role as a part of a construction project. However, considering the OSW, which has not been addressed in the project scheduling problems, requires the construction site to have a space capacity constraint while considering the workshop size, availability level, and other project-related constraints. In the present work, by considering the OSWs, a real construction project scheduling problem is studied as a Multi-Mode On-Site Workshop Investment Problem with Tardiness (MOSWIPT) while finding the installation/dismantling time of the OSWs. Two new (linear) mathematical programming models are proposed for MOSWIPT. Next, due to the NP-hardness of the problem, an enhanced Genetic Algorithm (GA)-based metaheuristic with efficient problem-specific improvement rules as local search and effective crossover and mutation operators is proposed. Computational experiments show that the proposed method has solved most of the instances of the addressed problem to optimality and outperformed the existing metaheuristics, e.g., Simulated Annealing (SA) and Particle Swarm Optimization (PSO). Finally, conclusions and suggestions for future studies are stated.</p><h2>Other Information</h2> <p> Published in: Heliyon<br> License: <a href="http://creativecommons.org/licenses/by/4.0/" target="_blank">http://creativecommons.org/licenses/by/4.0/</a><br>See article on publisher's website: <a href="https://dx.doi.org/10.1016/j.heliyon.2023.e22678" target="_blank">https://dx.doi.org/10.1016/j.heliyon.2023.e22678</a></p>
eu_rights_str_mv openAccess
id Manara2_350a2f59ade6bd13cc0ef21cf6a34513
identifier_str_mv 10.1016/j.heliyon.2023.e22678
network_acronym_str Manara2
network_name_str Manara2
oai_identifier_str oai:figshare.com:article/26642956
publishDate 2023
repository.mail.fl_str_mv
repository.name.fl_str_mv
repository_id_str
rights_invalid_str_mv CC BY 4.0
spelling On-site workshop investment problem: A novel mathematical approach and solution procedureNima Moradi (19418821)Vahid Kayvanfar (17876921)Roberto Baldacci (14779375)Information and computing sciencesData management and data scienceSoftware engineeringMathematical sciencesNumerical and computational mathematicsOn-site workshopProject schedulingMulti-mode resource investment problemGenetic algorithm<p>In real-world construction sites, On-Site Workshops (OSW) are installed to accelerate construction activities and facilitate the material handling process. These temporary OSWs are cost-effective, leading to decreasing the material handling cost and project makespan, which indicates their important role as a part of a construction project. However, considering the OSW, which has not been addressed in the project scheduling problems, requires the construction site to have a space capacity constraint while considering the workshop size, availability level, and other project-related constraints. In the present work, by considering the OSWs, a real construction project scheduling problem is studied as a Multi-Mode On-Site Workshop Investment Problem with Tardiness (MOSWIPT) while finding the installation/dismantling time of the OSWs. Two new (linear) mathematical programming models are proposed for MOSWIPT. Next, due to the NP-hardness of the problem, an enhanced Genetic Algorithm (GA)-based metaheuristic with efficient problem-specific improvement rules as local search and effective crossover and mutation operators is proposed. Computational experiments show that the proposed method has solved most of the instances of the addressed problem to optimality and outperformed the existing metaheuristics, e.g., Simulated Annealing (SA) and Particle Swarm Optimization (PSO). Finally, conclusions and suggestions for future studies are stated.</p><h2>Other Information</h2> <p> Published in: Heliyon<br> License: <a href="http://creativecommons.org/licenses/by/4.0/" target="_blank">http://creativecommons.org/licenses/by/4.0/</a><br>See article on publisher's website: <a href="https://dx.doi.org/10.1016/j.heliyon.2023.e22678" target="_blank">https://dx.doi.org/10.1016/j.heliyon.2023.e22678</a></p>2023-11-30T15:00:00ZTextJournal contributioninfo:eu-repo/semantics/publishedVersiontextcontribution to journal10.1016/j.heliyon.2023.e22678https://figshare.com/articles/journal_contribution/On-site_workshop_investment_problem_A_novel_mathematical_approach_and_solution_procedure/26642956CC BY 4.0info:eu-repo/semantics/openAccessoai:figshare.com:article/266429562023-11-30T15:00:00Z
spellingShingle On-site workshop investment problem: A novel mathematical approach and solution procedure
Nima Moradi (19418821)
Information and computing sciences
Data management and data science
Software engineering
Mathematical sciences
Numerical and computational mathematics
On-site workshop
Project scheduling
Multi-mode resource investment problem
Genetic algorithm
status_str publishedVersion
title On-site workshop investment problem: A novel mathematical approach and solution procedure
title_full On-site workshop investment problem: A novel mathematical approach and solution procedure
title_fullStr On-site workshop investment problem: A novel mathematical approach and solution procedure
title_full_unstemmed On-site workshop investment problem: A novel mathematical approach and solution procedure
title_short On-site workshop investment problem: A novel mathematical approach and solution procedure
title_sort On-site workshop investment problem: A novel mathematical approach and solution procedure
topic Information and computing sciences
Data management and data science
Software engineering
Mathematical sciences
Numerical and computational mathematics
On-site workshop
Project scheduling
Multi-mode resource investment problem
Genetic algorithm